Key Features
Construction of the concrete pavement for the NorthConnex Tunnel project –
- Construction of 9,280 sq.m of Hand Placed CRCP Pavement to varying widths. Works taken place on the shoulders and on various on/off ramps throughout the tunnel
- Construction of 16,600 sq.m of 4.3m Wide CRCP Pavement throughout various stages of the tunnel
- Slipform construction of 2km of modified Type F Barrier
- Modification of mould to slipform barrier linkups
- Compliance with strict tolerances as per Transport for NSW – Roads and Maritime specifications