Denham Court Road Upgrade

Client
Stockland
Value
Confidential
Period
2021
Location
Leppington, NSW
Expertise
Road Construction
Back to Projects

Key Features

Realignment and widening approximately 830m rural road to urban arterial Road. Works included:

  • Removal of vegetation and existing pavement
  • Earthworks along the extent of the proposed road re-alignment
  • Upgrade of the existing two-way road to a median separated, dual carriageway road of urban standard
  • Demolition of an existing bridge and construction of new twin bridges over the Heritage listed Water NSW Upper Canal.
  • Four-leg intersection complete with traffic signals
  • Three-leg, dual lane roundabout
  • Provision of off-Road shared pedestrian/cyclist paths and on-road cycle path along both sides of Denham Court Road for the length of the project
  • Provision of street lighting for the length of the project
  • Associated stormwater drainage works
  • Co-ordination of adjustments to public utilities such as electricity, communication, sewer and water services along the route
  • Construction of new twin bridges over the Heritage listed Water NSW Upper Canal.
  • Four-leg intersection complete with traffic signals
  • Three-leg, dual lane roundabout
  • Construction of a specially designed precast concrete protection slab over the existing Jemena 850mm diameter methane Gas main and APA 200mm diameter Ethane Gas pipeline