Key Features
Construction of over 1270 residential lots, inclusive of all infrastructure installation and road construction.
Stage 3C1 – $10.1 Million
- 211 Lot Residential Subdivision
- Installation of all services
- Importation of Fill Material – maintenance of council roads
- Service location and relocation
- Staggered service approvals/staging of works – complex project management
Stage 3C2 – $8 Million
- 165 Lot Residential Subdivision
- Importation of 125,000 cu.m of Fill Material
- Staging road construction, sewer service installation and retaining wall construction around import operations
- Redesign of sewer reticulation once works had commenced leading to an increase of sewer depth by 3 metres
- Achieving client deadline to enable settlement of lots before Christmas
- Construction of outlet structures to drain clean water into National Park
Stage 3C3 – $8.1 Million
- 165 Lot Residential Subdivision
- 16,526 sq.m of road pavement constructed
- 2,561 lin.m of stormwater drainage installed
- 4,555 sq. m of footpath constructed
- 116,502 sq.m of bulk earthworks completed
- Staging road construction, sewer service installation and retaining wall construction around
Village 5 – $8 Million
- 254 Lot Residential Subdivision
- Importation of 85,00 cubic metres of Fill Material
- Staging road construction, sewer service installation and retaining wall construction around import operations
- Achieving client deadline to enable settlement of lots before Christmas
- Construction of culvert structure beneath roads
Village 6 – $14.8Million
- 204 Lot Subdivision and construction of roundabout on live road to process access to the newly completed subdivision
- Importation of 110,00 cubic metres of Fill Material
- Management of local road network to allow importation of material at high volumes but also permit local and school traffic to operate as normal to minimise impact on community
- Simultaneous delivery of 2 Stages at once
- Interface of works with riparian corridors and the regional park
- Working adjacent to Xavier College for duration of works
- Delivery of accelerated program at client request under no margin for error
- Upgrade of local roundabout under live traffic conditions
- Significant amounts of community consultation and stakeholder management throughout entire duration of works
- Tree lopping in carriageway of live road
- Working around underground services and beneath powerlines
- Relocation of Telstra line fronting the stage in the road reserve underlying well established trees
Central Precinct 3A – $3.24 Million
- 80 lot residential subdivision inclusive of stormwater drainage installation, road construction, and services reticulation.
- Over 1,300 lin.m of storm water drainage including 600m of twin cell box culverts
- 10,000 sq.m of pavement to construct in various thicknesses
- Over 3,000 sq.m of footpaths
- The management of strict deadlines, delays in plan approvals, and changes to design during construction
Central Precinct 3B, 4A & 4B – $10.46 Million
- 194 lot residential subdivision inclusive of stormwater drainage installation, road construction, and services reticulation.
- Over 3,000 lin.m of stormwater drainage including 30m of triple-cell, stepped box culverts
- Over 25,000 sq.m of pavement to construct in various thicknesses
- Over 6,800 sq.m of footpaths
- The management of strict deadlines, delays in plan approvals, and changes to design during construction