Jordan Springs – Village 5

Client
Lendlease
Value
Confidential
Period
2014
Location
Jordan Springs, NSW
Expertise
Bulk Earthworks, Residential Subdivisions
Back to Projects

Key Features

Construction of a 254 lot residential subdivision, inclusive of extension bulk earthworks –

  • Importation of 85,00 cu.m of Fill Material
  • Staging road construction, sewer service installation and retaining wall construction around import operations
  • Achieving client deadline to enable settlement of lots in a specific timeframe
  • Construction of culvert structure beneath roads
  • Slipforming culvert slabs

Challenge

Jordan Springs Village 5 was the construction of a residential subdivision bordered on all sides by Regional Park.

This project required the construction of sizeable drainage on the border of the site in which JKW were able to develop a method of slipforming the culvert line slab with a reduced construction footprint. This project also saw the importation of fill through existing residential housing and other innovations with slipforming specialized kerb profiles required by the designers for management of traffic along the regional park.